STATE OF MICHIGAN
HOUSE OF REPRESENTATIVES OFFICE BUILDING
Lansing, Michigan
I. Project Description
The new State of Michigan House
of Representatives fourteen-story complex, built at a cost
of $40,000,000, brings State Legislators, their staff, and
the House support departments into one building centrally
located in downtown Lansing across the street from the historic
State Capitol. The location at the corner of Capitol Avenue
and Ottawa Street presented a winning opportunity for relocating
the 710 persons involved with the House of Representatives,
who previously occupied several buildings dispersed around
the city, into this class environment with adjacency to the
Capitol.
The House building comprised three individual structures framed
with a total of 2,540 tons of structural steel. The project
involved the redevelopment of two sites on either side of
Ottawa Street and the connection of those two sites. The result
presents two office towers with a third bridge building serving
as the connection. This three-part frontage afforded the opportunity
to develop identical office suites for all 110 Representatives,
each facing the Capitol Building. Feature windows, located
at each suite, provide views of the entire State of Michigan
government complex. Also featured are hearing rooms, a committee
center, conference and reception services, a lobby restaurant,
and underground parking.
The three major building components involved vertical expansion
of the City of Lansing Board of Water and Light Building from
a nine and five story to a fourteen-story tower, demolition
of an existing eight-story building and replacement with a
new eleven-story tower along with construction of a seven-story
bridge building suspended 65 feet over Ottawa Street.
II. Design and Construction Challenges
- Schedule
At the onset of the project, the design and construction
team was faced with a very aggressive schedule of twenty
(20) months from the inception through completion.
- Board of Water and Light Building
Vertical Expansion
Technically, most challenging was the existing Board
of Water and Light Building expansion. A portion of
the building had nine (9) floors, while the remaining
had five (5). The building program required addition
of five (5) and nine (9) levels respectively, on top
of the existing structural framework. It required considerable
structural upgrading to receive additional floor loads
and to resist lateral wind and seismic loads. New columns
were threaded through the existing floors to bear on
mini-pile foundations drilled through the basement floor.
During the construction, portions of the building were
still occupied by the Board of Water and Light employees.
This required new columns to be strategically located
and installed without disturbing the tenant spaces.
Columns with 2-inch thick flanges were full penetration
welded at the lower shaft splice points.
Lateral Load Resistance
The existing structure was designed with AISC type
2 connections to resist lateral loads. New braced bays
were added to resist current code required lateral loads.
The bracing connections needed to be custom fit to the
existing beam connections. At many locations, due to
space being occupied, permanent bracing could not be
installed. Desai/Nasr designed temporary bracing within
the existing structure to resist lateral loads, so that
precast panel erection could continue uninterrupted
to maintain aggressive project schedule.
Reinforcement of Existing Columns
and Beams
Many existing beams and columns were reinforced to
resist additional loading. In the extreme cases, beams
carrying concentrated loads from new columns were reinforced
with a heavy WT- section welded to the bottom flange
in conjunction with reinforcement of existing connections.
In many cases were columns needed reinforcement in two
or more adjacent levels, the engineers at Desai/Nasr
designed column reinforcement to be continuous through
penetrations in existing concrete floor. A typical configuration
consisted of four (4) plates each welded to one edge
of column flanges; this allowed reinforcing plates to
run through the floor without interference with beam-to-column
connections. This configuration also has the added advantage
of reversing the residual stresses in the existing column
thus favorably unleashing its reserve capacity. Several
other reinforcement configurations were designed to
accommodate various situations. Heavy WT-sections (e.g.
WT9x71.5) were used to reinforce exterior columns carrying
loads from nine (9) additional stories. In all cases
of column reinforcement, the effect of shift in column
centriod on load eccentricity was taken into consideration.
Interior Column Removal
Besides requiring localized reinforcement of beams,
columns and connections, it was discovered that in the
newly planned hearing room on the 5th floor an existing
column interfered with the Chairman's desk. This required
removal of a column between the 5th and 6th floors.
In order to move the interfering column, the adjacent
existing columns were reinforced. New W36 X 280 transfer
beams were threaded through one of the window openings,
raised to their final supporting positions, and attached
to the existing column. After all the connections were
made, the column was cut and removed. The beams were
designed to deflect due to dead load no more than 1/4"
to avoid cracking of four (4) supported floors above.
- North Capitol Building
In the mean time, Desai/Nasr and Douglas Steel determined
that it would be more cost effective to demolish the
eight-story structure across the Ottawa street, to accommodate
the 11 floors needed to provide the required square
footage. Desai/Nasr worked closely with the Project
Architect, Hobbs & Black, to determine the column
location to avoid interference with the existing structure
building. All the exterior columns had to be located
inbound by 8' from the exterior, and resulted in cantilevering
all 11 floors. Desai/Nasr and NuCon precast panel contractor
designed panel connections to the structure to accommodate
differential floor deflection at the cantilevered ends.
Small building footprint (70' X 70') compared to the
building height, (154') presented a challenge to resist
lateral loads. Rigid frames in combination with wide
flange K-braces were designed with high-strength bolted
connections to speed the erection of the frame.
- Ottawa Street Bridge Building
Desai/Nasr faced additional challenges in interfacing
the two towers located across the four-lane Ottawa Street
and designed three 30' deep Vierendeel trusses to support
seven floors totaling 37000 square feet space over the
street. The trusses were integrated into the three lower
floors and were primarily framed with W14X398 sections.
All the trusses were fabricated in Atree@ shapes with
full penetration welds and shipped from South Carolina
and field connected with over 7000 - 1 1/8" diameter
A490 bolts. Five-story shoring towers were erected on
mats beneath the tower to temporarily support trusses
until assembly and splicing were complete. Desai/Nasr
analyzed and designed the trusses to account for incremental
construction loads to ensure level floor elevations
in final use. The trusses were supported on 65 foot
high composite columns consisting of W14 x 398 steel
sections and 6000 psi concrete bearing on caisson foundations.
Due to below grade interference, the columns could not
be located to align with any of the nodes of the Vierendeel
truss. A special V shape knee bracing assembly was designed
at the top of the columns to transfer the forces from
the Vierendeel nodes to these columns. The Mackinac
Room located on the fifth floor of the bridge structure
with a stunning seven-story stained glass window provides
5000 sq.ft assembly space and features views of the
State Governmental complex on the west and the Grand
River and Lansing Convention Center on the east.
Due to the fast pace of construction on this complex
structure, fabrication was being performed as the design
was developing. Mill orders were placed based on initial
design, with final design and detailing being completed
as the raw material was arriving for fabrication. At
times fabrications was performed prior to shop drawing
approval with some modifications being made in the field.
The required modifications could not have been achieved
had the existing building been framed using reinforced
concrete.
- Engineering Software:
STAAD.Pro was used to verify the design of the Vierendeel
trusses and to calculate the axial loads in the Vierendeel
beams which could not be obtained from other programs
as most programs assign the axial force to the rigid
diaphragm. Other Engineering software such as Enercalc
and Ecom has been used for foundation design and for
analysis and design of individual steel and concrete
members. In-house computer programs were developed and
used to design and check column and beam reinforcement.
- Site Safety, Space Restrictions and Accessibility
Problems:
- Initially, steel erection had to be scheduled during
nights and weekends to assure the safety of the building
occupants working just below the new levels of steel.
Erection had to flow closely behind the surgical demolition
and abatement of the occupied building.
- In an attempt to manage the limited site space and
maximize the efficiency of the hoisting operation, Granger
Group took control of the crane, a 200 ton Manitowoc
M888. During periods of the project, steel was being
erected by day and precast by night using the same crane.
- Erection of the North Capitol Building was delicate
work as the new steel frame came within inches of a
neighboring historic landmark building.
- Satisfying Owner's Program
Mr. Bill Frank of Granger Group said: Desai/Nasr met
and exceeded Owner/Client's needs by utilizing reserve
capacity of the Board of Water and Light buildings=
columns and foundations, strategically locating and
designing new column locations so that the columns could
be installed while the building was still occupied.
Further, Desai/Nasr solved the problem of integrating
the two office towers located on each side of Ottawa
Street, by designing the 30' deep Vierendeel Trusses,
which allowed the owner to provide seven floors of the
office/assembly function spaces over a roadway. The
integrated 300,000 sq.ft structure provided a simple
and seamless flow of traffic for the staff, and easy
access for the visitors.
- Economic Impact
The House of Representatives building consolidated
all house offices and functions at one location. The
building also provided a permanent office for each district
and saved the Michigan tax payers the cost of moving
expenses estimated to be several thousand dollars after
each election year.
|